Wednesday, July 30, 2014

Plugging Along

So far so good. We have been fortunate to have crews and subs available pretty consistently to keep this project moving forward. The Studio Build guys have been all over it and we should be turning a corner shortly. The rough plumbing is completed and the floor is getting replaced today. I stopped by this morning and the HVAC guy was finishing duct work and getting ready to set the AC and furnace.
It was a big blessing in disguise that the old concrete tile roof was shot and had to go. After pulling it off no amount of repair was going to stop the leaks. Now we have a nice new 50 year roof. All of the facia was rotten or missing and we went back with hardiboard, so no worry about rot in the future. The flat roof section had sagged and leaked where it joined the sloped roof. It is now pitched out for positive drainage. Combine that with a bunch of new roof vents and it looks like a new house.

The front porch had dropped 6 inches from some very old termite damage. It got jacked up and is held in place by a new tapered column. Fortunately there was a brick ranch just down the street with tapered columns so we didn't have to go far for inspiration.

And a view of the family room from the front yard. The blocked out window space is where the new second bathroom is going. 
Next Few Weeks:
- Interior Plumbing
- Electrical
- HVAC

Thursday, July 17, 2014

Sometimes It Gets Worse Before It Gets Better

The project is in full swing. We don't have internet at the apartment so the posts are a few and far between. The past few weeks have brought lots of demo and things are starting to go back together.
The house had an original drywall that was finished with mortar. It was solid. The demo guys didn't appreciate the craftsmanship.
 
All of the walls have been demo'd and reframed. The floor is cut up to run new plumbing. The main stack was cracked so everything had to go. We moved a wall to make the kitchen bigger and vaulted the ceiling which will really improve the space.
 
The kitchen cabinets have gone to powder coating so the only things in the guest bedroom/office are the appliances. From the outside you would guess that it had originally been a two car garage and they just walled off one bay. That wasn't the case. As you can see there is three feet elevation difference between the garage and the rest of the house, strange.
 
The roof was in really bad shape and we are getting it replaced. The flat portion in the back was waterproofed with soldered tin. No amount of patching was going to fix that.  
 In the next couple weeks it will start coming together with the roof, HVAC, electrical, plumbing, and insulation all happening.